Front End Engineering and Conceptual Design

Sample Projects

  • Pilot Plant Equipment Design

    1. Main Problem Identified: Full system design for a high-temperature, specialty production pilot plant.

    2. Approach: Created multi-system design basis documentation covering reactor, tanks, piping, and auxiliary vessels using ASME Section VIII concepts where applicable.

    3. End Results: Design package delivered with detailed vessel specs, safety margins, and equipment integration strategy for all pressure equipment. Readied for vendor fabrication

  • Pressure Vessel Shop Audit

    1. Main Problem Identified: Concerns regarding a fabrication company’s capabilities to manufacture a nickel alloy (Alloy 625) vessel with sufficient quality and schedule control.

    2. Approach: Performed two-day onsite fabrication shop audit. The evaluation included interviews with staff, walk-through of fabrication facilities, review of procedures, equipment, project tracking systems, inspection of alloy handling, welding practices, engineering team qualifications, subcontracting dependencies, and contamination control practices.

    3. End Results: The fabricator was deemed limited but competent with consistent quality in core capabilities. No red flags were found that would necessitate removing the vessel from the company’s scope. Confirmed confidence in fabricator’s ability to fabricate the vessel. Recommendations provided: Implement protective handling protocols for Alloy 625. Engage a qualified Welding Engineer to review new weld procedures Require a formal Inspection and Test Plan (ITP) to control fabrication hold points

  • Evaluation Of Design Codes

    1. Main Problem Identified: Uncertainty around potential benefits of using ASME Section VIII, Division 2 for new vaporizer exchanger design

    2. Approach: Compared minimum thicknesses and maximum allowable pressures across all major components using COMPRESS software; applied MA46 to isolate impacts of design margins vs. equation conservatism.

    3. End Results: Found minor efficiency gains (~8–10%) in wall thickness and allowable pressure for external pressure components; recommended continued use of Division 1 due to minimal savings, higher fabrication costs, and tighter tolerances required under Division 2.

  • Purchasing Spec Creation

    1. Main Problem Identified: An in-service reactor vessel had widespread internal erosion, driving remaining wall below site minimums and making repair uneconomical ahead of a planned turnaround. A replacement was required, but prior procurements suffered from inconsistent vendor assumptions that led to change orders, nozzle misalignment, and schedule risk.

    2. Approach: A comprehensive Mechanical Purchasing Specification (M-Spec) was authored to define design and construction requirements per ASME Section VIII, Division 1 with supplementary analysis where nozzle external loads warranted, including MAWP/MDMT, corrosion allowance, materials, impact testing, NDE, PWHT, coatings, and nameplate/U-stamp requirements. The deliverables included purchasing and bid requirements (schedule, pricing breakdown, exceptions register), a process/mechanical datasheet, conceptual GA drawings with nozzle map and allowable external loads, and a vendor data/ITP matrix with hold points, MDR content, shipping/lifting instructions, and preservation criteria.

    3. End Results: The standardized package yielded three fully compliant “apples-to-apples” bids with fewer than five minor exceptions, eliminating scope ambiguity across vendors. The selected fabricator committed to an acceptable turnaround cycle and a cost reduction versus the last comparable buy, and IFC vendor drawings matched existing foundations and centerlines with minimal RFIs during installation. The new vessel entered service with leak-free performance and documentation complete for turnover.

  • Design of Replacement Heat Exchanger

    1. Main Problem Identified: Need to increase design pressure on the tube side of six identical, new exchangers beyond original design of old equipment.

    2. Approach: Performed ASME Section VIII, Division 1 assessment using COMPRESS software. Completed review of shell and tube side MAWP and required thickness calculations. Tubesheet and nozzle re-evaluation was necessary for higher pressures.

    3. End Results: Tube side successfully redesigned for increased design conditions on replacement exchangers. Only minor physical modifications required; gasket and bolt configuration was maintained. Supports operational flexibility with increased throughput.

Connect with an Engineer

Contact us today for support with your pressure equipment design and analysis needs.

operations@refinedengineering.com

+1 (833) 313-4873

Next
Next

Mechanical Design & Analysis