Suitability and Compliance Assessments

Sample Projects

  • Drum State Special Application

    1. Main Problem Identified: A legacy flare drum built without ASME U-stamping was converted to flare service and, in rare upsets, could exceed normal low-pressure operation; current mitigations cap the upset pressure that was still above the 15 psig threshold for the state. The objective was to formally qualify the vessel for State Special status at the required design conditions and present the application to the state’s pressure vessel boad.

    2. Approach: Section VIII-1 calculations were performed in COMPRESS using conservative material properties and joint efficiency assumptions aligned with the state’s Boiler & Pressure Vessel Safety Regulations, supported by an external inspection and 100% PAUT of welds. A stepwise plan covered submittal for state review, conditional approval, a hydrotest, and final internal inspection with witnessed nameplate application. Component thicknesses in the model were taken as the lesser of the 1963 drawings and the latest UT survey to maintain conservatism.

    3. End Results: Code results demonstrated adequacy at the requested design conditions providing substantial margin. With the upset pressure limited, the vessel proceeded with a hydrotest and final internal inspection en route to nameplate application. The drum was approved for State Special status and is in operation.

  • Low-Pressure Torispherical Head Evaluation

    1. Main Problem Identified: A polymer storage tank’s bottom torispherical head was originally designed for very low uniform internal pressure (<1 psig) without explicitly accounting for the much higher hydrostatic head at the bottom, necessitating a combined-loading reassessment. The thin head’s knuckle region was expected to be buckling-susceptible under compression, making the head the limiting component.

    2. Approach: Design-by-rule head checks (ASME VIII-1 Appendix 1-4) were used for screening only, recognizing they can be overly conservative for this geometry and that the attached half-pipe coil materially stiffens the head. A Design-by-Analysis was performed per ASME VIII-2 Part 5 using elastic-plastic FEA (ABAQUS), with factored vessel pressure and hydrostatic head (and, where applicable, jacket pressure) to evaluate plastic collapse and buckling. Multiple load cases were studied.

    3. End Results: The unstiffened head did not satisfy code margins in plastic-collapse or buckling checks, whereas coil-stiffened cases converged and met the required design margins. Incorporating the half-pipe coil significantly increased head stiffness and pressure capacity, with the knuckle remaining the governing location under internal pressure. Thus, when evaluated by VIII-2 Part 5 methods under the governing combined-loading case, the head and shell were acceptable for the rating envelope.

  • Minimally Documented Drum Evaluation

    1. Main Problem Identified: Two large helium storage tanks needed to be qualified for higher internal pressure and a vacuum rating before being placed back into service. The key objective was to establish updated allowable ratings (MAWP/MAEP) using modern Code rules given limited legacy design documentation. Only a Form U-1 and nameplate were available.

    2. Approach: The tanks were modeled in COMPRESS and evaluated per ASME VIII-1 using post-1999 allowable stresses; assessments focused on pressure loads only. As-built data from a field walk-down informed the model, and governing components for internal and external pressure were identified to determine controlling ratings; corrosion allowance was set to maximize allowable pressure in a non-corrosive service.

    3. End Results: The evaluation established MAWP, MAEP, and MDMT. A hydrotest is required (greater than the original), after which formal rerating can proceed with no physical tank modifications.

  • Bolted Flange Joint Procedure

    1. Main Problem Identified: The project team needed a plant-wide, standardized process for bolted flange joint assembly to eliminate inconsistent practices in surface prep, gasket handling, bolt lubrication, and tightening methods. Without a single controlled procedure, the risk of startup leaks and rework across contractors remained unacceptably high.

    2. Approach: A site-specific BFJ procedure was authored to define responsibilities, required materials, step-by-step assembly (clean/inspect, fit-up, multi-pass cross-pattern tightening, verification), tool calibration, and documentation requirements. The package included calculated target torque/tension tables by flange class and stud size, acceptance/hold criteria, troubleshooting guidance, and pre-/post-job QA/QC checklists for consistent execution from construction through commissioning. The document was issued as a controlled procedure for training and rollout.

    3. End Results: The finalized procedure, torque tables, and sign-off forms provided a single, auditable method that improves bolt-load consistency and reduces the likelihood of leak-induced delays. The package was approved for site use and incorporated into contractor workflows to support reliable startups and repeatable maintenance.

  • Silo Explosion Panel Opening Analysis

    1. Main Problem Identified: New explosion-capacity requirements drove larger and/or additional explosion panels in two polymer silos, raising concerns about plastic collapse, buckling, and serviceability with the proposed rectangular openings. The plant also needed to know if added reinforcement (e.g., repads) was necessary and what weld detail could avoid interior scaffolding.

    2. Approach: A design-by-analysis evaluation per ASME Section VIII, Division 2 Part 5 used nonlinear elastic–plastic FEA for plastic collapse and elastic bifurcation analysis for buckling, with acceptance based on achieving convergence at factored loads for API-620 construction and a serviceability limit. Models of both silos (no reinforcement added at openings) were analyzed at MAWP, assumed vacuum, and explosion conditions, and wind/seismic were screened as negligible compared to pressure.

    3. End Results: Both silos met design and serviceability criteria without requiring reinforcement around the new/modified openings; max deformations and strains were acceptable. Buckling margins were ample and rotating the new opening was recommended to ease fit-up and reduce local stress; a single-sided bevel with fillet cap was proposed as the weld detail.

  • Reactor Main-Body Flange Assessment

    1. Main Problem Identified: Historical leakage at the body flange pairs—exacerbated around a jet-fire event—raised concerns about flange integrity, bolt preload adequacy, and gasket seating during start-up/shutdown thermal transients. The previously applied bolt stresses were well below ASME PCC-1’s recommended values against yield, and the joint’s high gasket-to-bolt area ratio made reliable seating especially challenging.

    2. Approach: The flanges were reassessed using ASME VIII-1 Appendix 2 design-by-rule, complemented by ASME VIII-2 design-by-analysis with WRC-538 stress limits and a detailed 3D FEA section model of the worst-case reactor, incorporating nonlinear gasket load/unload behavior. Both steady-state and transient thermal cases (normal start-up/shutdown, fire shutdown, and a 100 °F/hr ramp) were evaluated for gasket contact pressure, bolt stress versus PCC-1 70%-of-yield guidance, flange rotation, and hub/shell stress classifications. Modeling captured realistic boundary conditions, convection coefficients, preload variants, and internal pressure/thrust loads to identify governing behaviors.

    3. End Results: The flange design demonstrated adequate mechanical integrity with no fundamental design deficiency; leakage susceptibility was attributed primarily to low assembly preload combined with the joint geometry. A 70%-of-yield preload achieved near-optimum average gasket seating while remaining acceptable for flange and bolt stresses, whereas the historical preload barely met minimum seating and allowed ID unloading at operating conditions. Transient checks indicated the joint could tolerate a modest thermal ramp structurally, but the OD of the gasket may crush under that scenario; the prior jet fire was not shown to have caused permanent flange damage.

  • Reactor Bed dP Capacity Assessment

    1. Main Problem Identified: Operational differential pressure (dP) at an intermediate catalyst bed was trending toward the historical design limit, prompting concern that the existing dP basis was inadequate for current conditions. The goal was to determine an upper-bound dP capacity for the corroded bed support while preserving an assumed design margin.

    2. Approach: An API 579-1/ASME FFS-1 limit-load assessment with nonlinear FEA was performed, applying the global load combinations to demonstrate protection against collapse. A quarter-symmetry 3D model explicitly captured the shell segment, support ring and lugs, primary beams, grating, and braces; loads included catalyst deadweight and applied dP, with tie and contact interactions. Material properties were elastic-perfectly-plastic per ASME II-D at temperature, and convergence at the factored load defined capacity.

    3. End Results: The bed met the required margin at an increased dP with global collapse in the inner beams governing; torsional buckling was screened as non-controlling. Recommendations included confirming remaining beam thickness and considering support modifications if still more capacity is needed.

  • PWHT Structural Stability Evaluation

    1. Main Problem Identified: During local postweld heat treatment of a vertical reactor exchanger at approximately 1,175 ± 25 °F, reduced shell strength under heat plus wind and deadweight raised the risk of short-term (creep) buckling. The support legs would be limited to ≤900 °F, but confirmation was needed that both shell and legs would remain stable without temporary external supports via a crane during the PWHT.

    2. Approach: A short-term buckling assessment was performed using API 579/ASME FFS-1 methods and inelastic/creep buckling approach, developing an isochronous stress–strain curve. Stresses from deadweight and a conservative wind load were calculated via a COMPRESS model and compared to allowable buckling stress; support legs were evaluated per AISC at 900 °F using interaction equations.

    3. End Results: The compressive stress at the bottom of the PWHT band was well below the allowable buckling stress, with wind governing, so shell buckling during PWHT was not a concern. The legs satisfied AISC interaction checks and no supplemental supports were required for the heat treatment.

  • Nozzle Cracking Failure Assessment and Repair

    1. Main Problem Identified: Cracking discovered at the weld between the inlet nozzle and shell of a stainless steel deaerator. Similar defects had been discovered at similar locations on other deaerators for the client.

    2. Approach: Working with a metallurgical lab, destructive testing was performed to confirm the damage mechanism of the crack. Reviewed existing operating procedures and the physical characteristics of the inlet nozzle as well.

    3. End Results: The damage mechanism was determined to be Caustic SCC from a combination of a poorly designed pH control system and non-standard hopper design. Redesigned the nozzle-hopper configuration to lower over-constraint and upgraded the local metallurgy since the pH control system was not readily modified.

Connect with an Engineer

Contact us today for support with your pressure equipment design and analysis needs.

operations@refinedengineering.com

+1 (833) 313-4873

Previous
Previous

Fitness-for-Service

Next
Next

Project & Turnaround Support